Project timeline
The project is scheduled to be implemented within 24 months from July 21, 2025.
The implementation of the project is divided into the following phases:
- Initial Phase – 1 month after the contractor is engaged;
- Optimization Phase (1 month) – conducting semi-industrial trials to adjust production parameters and optimize the transport and loading of ash;
- Implementation Phase (21 months) – phase of ash collection and utilization;
- Project Closure Phase (1 month) – summarizing results and preparing the final report.
All phases are sequential and begin after the completion of the previous phase.